The PMI Risk Management Professional (PMI-RMP) exam focuses on a broad spectrum of risk topics and concepts. Among the major risk areas are government, market laws/rules, organizational, environmental, and technical risks. By understanding these risks, future project managers can significantly heighten their level of project risk management awareness and more effectively respond to potential hazards.
Governmental Risks:
Government bodies, in particular, are inextricably linked to such things as permits, tax laws, and general regulatory functions. Their influence on your project can pose substantial risks. Changes to regulations or alterations in taxation can delay projects, inflate costs, or force project modifications.
Example: A company is engaged in a construction project within a particular district. Halfway within the project, the local government modifies its building regulations, basing these on new safety standards. As a result, the company then has to change its project plan to meet the new requirements.
Market laws/rules risks:
Market laws or rules pertain to the business and industry-specific regulations or norms that can impact a project’s progress, a product’s acceptance, or a company’s operation.
Example: A pharmaceutical firm working to develop a new drug must closely monitor and comply with the strict regulations set by the Food and Drug Administration (FDA). Any deviation or failure to meet these requirements can not only halt the project’s progress but also pose significant financial and reputational risks to the company.
Organizational Risks:
Organizational risks are those associated with the structure, culture, and efficiency of the organization executing the project. These include anything from leadership turnover, changes in management methods, cultural changes, or shifts in organizational strategy.
Example: If a manufacturing enterprise decides to implement a new production process, it might face resistance from employees accustomed to the old methodology. This resistance can delay the project and lead to detrimental productivity losses.
Environmental Risks:
Environmental risks refer to the significant external factors that can negatively impact your project. These factors can include natural disasters, political instability, or even fluctuations in the economy.
Example: A construction project in a region known for heavy seasonal rainfall can face extensive delays, extra expenses, and possible structural damages.
Technical Risks:
These are risks associated with the actual technical processes of project implementation, including the potential for technological failure, design shortfalls, or quality control problems.
Example: An IT company working on a new software application can face technical risks such as unexpected bugs, technical complexities not originally accounted for, or an inability to integrate with existing systems.
In Conclusion:
In conclusion, understanding these broad categories of risks is key for successful project risk management. Each of the categories – government, market laws/rules, organizational, environmental, and technical risks – require detailed risk analysis, strategic planning, and correct risk response strategy as they all are an inherent part of the PMI Risk Management Professional (PMI-RMP) exam preparation.
Practice Test
True or False: Government risks refer to potential losses due to changes in government legislation and policies.
• True
• False
Answer: True
Explanation: Government risks involve changes in government legislation and policies that can affect the project’s outcome, such as new laws, changing policies, and reshuffling of government.
What is organizational risk in the context of project management?
• A. Risk of natural disasters
• B. Risk of changes in management
• C. Risk of change in market laws
• D. Risk of software malfunction
Answer: B. Risk of changes in management
Explanation: Organizational risks refer to those risks associated with the style of project management within the organization. They can include aspects like changes in management, restructuring, or internal politics.
Environmental risks in project management primarily focus on:
• A. Compliance with environmental laws
• B. Natural disasters or extreme weather events
• C. Both A and B
• D. Neither A nor B
Answer: C. Both A and B
Explanation: Environmental risks refer to both natural disasters which can hamper the progress of the project and the need to comply with environmental laws and regulations.
True or False: There is no relationship between market laws and risks in project management.
• True
• False
Answer: False
Explanation: Market laws can significantly affect the project’s success. Changes in market laws can pose a risk if they affect aspects of the project such as cost, timeline, or deliverables.
Technical risks in project management can include:
• A. Changes in software requirements
• B. Technological advancements
• C. Cybersecurity threats
• D. All of the above
Answer: D. All of the above
Explanation: Technical risks refer to uncertainties in technologically intensive systems that can have negative effects on the project outcomes, including software changes, advancements, and threats.
True or False: PMI Risk Management Professional (PMI-RMP) focuses primarily on financial risks.
• True
• False
Answer: False
Explanation: The PMI-RMP certification acknowledges a professional’s ability to identify and assess project risks while mitigating threats and capitalizing on opportunities. It covers more than just financial risks.
Government risks can be avoided through:
• A. Regular monitoring of legislative changes
• B. Hiring knowledgeable local professionals
• C. Both A and B
• D. Neither A nor B
Answer: C. Both A and B
Explanation: Both regular monitoring of legislative changes and hiring knowledgeable local professionals can help in avoiding government risks.
Which of the following is not an example of an organizational risk?
• A. Change in executive leadership
• B. Data breach
• C. Employee turnover
• D. Natural disaster
Answer: D. Natural disaster
Explanation: A natural disaster would fall under environmental risks, not organizational risks.
Which type of risk would potential changes in tariffs and trade agreements fall under?
• A. Technical risks
• B. Market risks
• C. Government risks
• D. Organizational risks
Answer: C. Government risks
Explanation: Changes in tariffs and trade agreements are usually linked to government policies so they would be categorized as government risks.
Which among the following constitutes a technical risk?
• A. Change in government policy
• B. Change in project scope
• C. Software malfunction
• D. Increase in competition
Answer: C. Software malfunction
Explanation: Technical risks are those that are associated with the use of technology in a project, such as software glitches or malfunction.
Interview Questions
What is the principle of the “Government Risks” in the PMI-RMP exam?
The principle of “Government Risks” refers to the adverse impact on a project due to changes in government regulations, rules, and laws.
What is a market risk in project management?
A market risk involves the probability of an investment’s actual returns will significantly differ from expected returns due to changes in market conditions or wrong market predictions.
According to the organizational risk environment, what is risk tolerance?
Risk tolerance is the degree of variability in investment returns that an organization is willing to withstand in their risk management practices. It determines the level of risk the organization can comfortably manage.
How does technical risk affect project management?
Technical risks are associated with the developing technologies involved in the project. Inadequate technical analysis can lead to project failures, cost escalations, and time delays.
How can environmental risks impact a project?
Environmental risks involve unexpected or adverse conditions in the environment that might negatively impact the project. These can include natural disasters, harsh weather conditions, or regulatory changes in environmental law.
What does a regulatory risk pertain to in the context of PMI-RMP?
Regulatory risk pertains to potential losses an organization may suffer due to changes in laws or regulations, or due to non-compliance with existing regulations.
What is the importance of risk management under PMI-RMP?
Risk management is essential as it helps organizations anticipate and mitigate possible adverse events. It ensures efficiency, effectiveness, and consistency in managing risks, deters potential legal actions and safeguards the organization’s reputation.
How do political risks affect project management?
Political risks such as changes in policies, regulations, government instability, and wars can significantly affect the operational, financial, and market performance of a project.
How does a project manager identify a market risk?
A project manager identifies a market risk by conducting a risk identification process which involves market research, SWOT analysis, forecasting, and utilizing specialized risk identification tools and techniques.
What is risk appetite in PMI-RMP?
Risk appetite is the level of risk an organization is prepared to accept to achieve its objectives, before action is deemed necessary to reduce the risk. It is usually measured in terms of potential impact on project objectives.
What are some common organizational risks?
Common organizational risks can include internal changes in management or strategy, workforce changes, restructuring, or other internal disruptions.
How can technical risks be mitigated?
Technical risks can be mitigated by using proven technology, regular quality checks, adhering to technological standards, pilot testing and phased implementation.
What role does risk analysis play in PMI-RMP?
Risk analysis is used to understand the risk events, their relationships, and to evaluate the potential impact on project objectives. It is the basis for risk response, mitigation, or transfer decisions.
What is environmental risk management?
Environmental risk management involves identifying, assessing, and controlling risks arising from operational factors. It could include risks related to pollution, natural disasters, or other environmental conditions.
How can understanding market laws/rules help in managing risks?
Understanding market laws/rules can provide insights into potential regulatory risks, effectively plan for regulatory changes, and stay compliant thereby reducing potential losses and penalties.