For someone preparing for the Certified Scrum Developers (CSD) exam, it’s particularly important to comprehend the organization and demonstration of the Daily Scrum, serving as a substantial part of the Scrum process.
I. Understanding the Daily Scrum
The Daily Scrum is a brief, time-boxed event dedicated to the Development Team. It typically lasts for 15 minutes and happens at the same place and time every day.
During this meeting, each member of the Scrum Team answers three crucial questions:
- What did I do yesterday that helped the Development Team meet the Sprint Goal?
- What will I do today to help the Development Team meet the Sprint Goal?
- Do I see any impediment that prevents me or the Development Team from meeting the Sprint Goal?
This dialog provides each team member with a clear understanding of what has been accomplished and what remains to be done. Moreover, it facilitates quick detection and resolution of possible impediments and maintains a healthy, transparent collaboration within the team.
Despite the general perception, the Daily Scrum is not a status update meeting, but rather a chance for the Development Team to inspect and sync their own work and plan the work for the next 24 hours.
II. Organizing the Daily Scrum
Organizing the Daily Scrum includes the following components:
- Setting the Scene: The meeting should be set at the same place and time every day to create consistency. Some Development Team might choose a physical room whilst others might opt for a virtual platform.
- Preparation: Each team member comes prepared to discuss their work. They would need to have clear ideas on the work they did, the work they plan to do, and highlight any impediments that need to be handled.
- Time-box: To maintain a focused discussion and not diverge into detailed problem-solving, the meeting should be time-boxed to 15 minutes.
- Required Participants: Every member of the Development Team is required to attend. The Scrum Master ensures the event occurs but their attendance is not mandatory unless necessary. Other stakeholders can attend as listeners but do not actively participate.
III. Demonstrating the Daily Scrum
Demonstration of the Daily Scrum can be facilitated by using the Scrum board that visually shows the tasks for the current Sprint divided into three sections: To-Do, In Progress, and Done.
Here’s an example:
To-Do | In Progress | Done |
---|---|---|
Develop contact us form | Testing login feature | Debug homepage |
Design user profile page | Research chatbot implementation | Finalize site map |
Implement email notifications |
A properly organized and conducted Daily Scrum increases team productivity by helping the team to stay aligned on the project’s progress. It ultimately amplifies the Scrum framework’s benefits, which in turn, leads to more successful projects. Whether you’re preparing for the CSD exam or trying to improve the agile practices within your organization, mastering the Daily Scrum is a fundamental component to success in Scrum.
Practice Test
True or False: The Daily Scrum should last no more than 15 minutes.
- True.
Answer: True.
Explanation: The Daily Scrum is a ceremony where the team synchronizes activities and makes a plan for the next 24 hours. It is supposed to be a quick check-in and should therefore not last more than 15 minutes.
Who primarily drives the Daily Scrum?
- a) Scrum Master
- b) Product Owner
- c) Development Team
Answer: c) Development Team
Explanation: The Daily Scrum is for the Development Team to synchronize their work and plan for the next 24 hours. While the Product Owner and Scrum Master may be present, it is the Development Team that should be driving the meeting.
True or False: The Daily Scrum meeting is the time for problem-solving and task assignment.
- False.
Answer: False.
Explanation: The daily Scrum is mainly for synchronization, updates and planning the next day’s work. Detailed issue discussions, problem-solving, and task assignments should take place outside the daily Scrum.
Which of the following is NOT a question typically addressed in the daily Scrum?
- a) What did I do yesterday that helped meet the Sprint Goal?
- b) What will I do today to help meet the Sprint Goal?
- c) Who is to blame for the missed deadlines?
- d) Do I see any impediments that could prevent the team from meeting the Sprint Goal?
Answer: c) Who is to blame for the missed deadlines?
Explanation: The daily Scrum is not a blame game. It is conducted to plan, synchronize activities, and identify potential impediments.
True or False: The location and time of the daily Scrum changes each day.
- False.
Answer: False.
Explanation: For the sake of consistency, the time and location of the daily Scrum should be fixed.
The ultimate responsibility for the daily Scrum meeting lies with the:
- a) Development Team
- b) Scrum Master
- c) Product Owner
- d) Managers
Answer: b) Scrum Master
Explanation: The Scrum Master ensures that the Development Team has the daily Scrum meeting, but the Development Team is responsible for conducting the meeting.
True or False: Even if not all team members can attend, the daily Scrum should still happen.
- True.
Answer: True.
Explanation: The daily Scrum should not be delayed or skipped due to non-availability of some team members. The meeting is important because it helps synchronize the work of all Team members.
The primary purpose of the daily Scrum is?
- a) To provide status updates to management
- b) Problem-solving and brainstorming
- c) Align the development team and identify impediments
- d) To assign tasks for the day
Answer: c) Align the development team and identify impediments
Explanation: The main purpose of the daily Scrum is for the development team to synchronize their work and identify any blocks that could be slowing progress.
True or False: Anyone can attend the daily Scrum.
- True
Answer: True
Explanation: While the meeting is primarily for the Development Team, Scrum values openness and transparency and accordingly, anyone may attend though they are only observers if they are not Development Team members.
During the Daily Scrum, the Development Team focuses on?
- a) The sprint backlog
- b) The product backlog
- c) The meeting minutes
- d) The burndown chart
Answer: a) The sprint backlog
Explanation: The development team focuses on what’s in the sprint backlog and how to achieve the sprint goal during the daily Scrum. The product backlog may be addressed in grooming sessions and sprint planning meetings instead.
Interview Questions
What is the primary objective of a daily Scrum meeting?
The primary objective of a daily Scrum meeting is to synchronize the work of the team members, make necessary adaptations to the backlog, and highlight any potential blockers.
What is the recommended duration for a daily Scrum meeting?
The recommended duration for a daily Scrum meeting is 15 minutes.
What are the three common questions that each team member answers during a daily Scrum meeting?
The three common questions are: What did I complete yesterday? What will I work on today? Are there any blocks or impediments in my way?
Who facilitates the daily Scrum meeting in a Scrum team?
The Scrum Master typically facilitates the daily Scrum meeting.
Is the Product Owner required to attend the Daily Scrum?
While their attendance is not mandatory, it can be beneficial for the Product Owner to attend to stay informed of development progress and potential obstacles.
Who can change the Sprint Backlog during a Sprint?
Only the development team can change the Sprint Backlog during a Sprint.
When should the Daily Scrum occur?
The Daily Scrum should occur at the same time and place each day to reduce complexity.
What happens if the Product Owner is not available to attend the Daily Scrum?
The Daily Scrum proceeds as usual, but the Scrum Master or a team member must update the Product Owner on any important information they missed.
Should stakeholders attend the Daily Scrum?
No, stakeholders should not attend the Daily Scrum as it is a meeting for the Scrum Team. They are welcomed at the Sprint Review however.
Who is responsible for removing the obstacles mentioned during a Daily Scrum?
The Scrum Master is responsible for removing the obstacles or helping the team remove them.
What should team members do if a detailed discussion starts during the Daily Scrum?
Detailed discussions should be taken outside of the Daily Scrum. The Daily Scrum should be a quick synchronization and planning meeting.
What happens if the work for the Sprint is not completed at the end of a Sprint?
The remaining work is re-estimated and prioritized. The Product Owner may choose to include it in the backlog for future Sprints.
How are the results of the Daily Scrum used in Scrum project management?
The results of the Daily Scrum are used to update the Sprint Backlog, adjust the Sprint plan if necessary, and identify any necessary coordination between team members.
What role does the Scrum Master play in the Daily Scrum?
The Scrum Master facilitates the meeting, ensures everyone has an opportunity to speak, keeps the team focused on answering the three questions, and helps remove any identified obstacles.
Is the Scrum Master responsible for ensuring that the team meets the Sprint goal?
No, the entire Scrum team is collectively responsible for meeting the Sprint goal, although the Scrum Master plays a supportive role in this process.