Performing qualitative analysis in the area of risk management involves identifying potential risks and assessing their impacts on a project. This step is crucial as it allows for effective risk prioritisation by determining the probability and impact of risks. For PMI Risk Management Professionals (PMI-RMP), performing qualitative analysis effectively can significantly improve the outcomes of the project.

Table of Contents

Understanding Qualitative Risk Analysis

According to the Project Management Institute (PMI), qualitative risk analysis is an approach that allows for the prioritisation of risks based on their potential effect on project objectives. This method uses likelihood or probability and impact scales to rank and prioritise risks. Often, it is carried out after risk identification but before quantitative risk analysis, and it forms part of the overall risk management process.

In conducting qualitative risk analysis, the process is typically iterative—not a one-time event. This is due to the changing environment of projects or periodic reviews that might introduce new risks or change the characteristics of existing risks.

Techniques in Qualitative Risk Analysis

One common technique in conducting qualitative risk analysis is the Risk Probability and Impact Matrix. In this matrix, the probability and impact of each identified risk are assessed and scored on a numerical scale (usually 1 to 5 or 1 to 10), or a descriptive scale (like low, medium, high). Below is an example of this matrix:

Low Impact Medium Impact High Impact
High Probability H
Medium Probability M
Low Probability L

(L represents Low risk, M represents Medium risk, H represents High risk).

Another technique is the Risk Data Quality Assessment. This technique evaluates the extent to which the risk is understood, the availability of risk data, data quality and reliability, and integrity of the data.

Importance of Qualitative Risk Analysis

The importance of qualitative risk analysis in project management cannot be overstated. Its benefits include:

  • Prioritisation of Risks: Qualitative analysis assists in distinguishing high-priority risks that need immediate attention from lower priority risks.
  • Increasing Risk Knowledge: It enhances the understanding of risks, their causes, and how they might affect project objectives.
  • Determining Risk Response: Inputs from this analysis serve as a guide in devising risk response strategies.

Qualitative Analysis in PMI-RMP Exam

In the PMI-RMP exam, understanding and demonstrating competency in qualitative risk analysis is vital. Test items may include case studies requiring the implementation of the Risk Probability and Impact Matrix or the Risk Data Quality Assessment to identify and prioritise risks.

In summary, qualitative risk analysis plays a pivotal role in managing risks effectively. For PMI-RMP professionals, mastering the techniques and understanding the importance of this analysis will not only enhance performance in real-world project scenarios but also increase the probability of success in the PMI-RMP exam.

Practice Test

True or False: Qualitative analysis involves a numerical assessment of the risk.

  • True
  • False

Answer: False

Explanation: Qualitative analysis refers to the process of identifying, assessing, and prioritizing risks based on their likelihood of occurring and the magnitude of their impact. It does not involve numerical assessment.

The first step in conducting a qualitative risk analysis is:

  • A. Rank the risks
  • B. Collect data
  • C. Identify the risks
  • D. Develop a risk register

Answer: C. Identify the risks

Explanation: The first step in conducting a qualitative risk analysis is to identify the risks. This involves identifying potential risk events, their causes, and their potential impacts.

Which of the following is NOT part of qualitative risk analysis?

  • A. Identifying the risks
  • B. Ranking the risks based on their potential impact
  • C. Calculating the monetary value associated with each risk
  • D. Determining the likelihood of each risk

Answer: C. Calculating the monetary value associated with each risk

Explanation: Calculating the monetary value of each risk is a part of quantitative risk analysis not qualitative.

True or False: Qualitative risk analysis should be performed during the planning process of a project.

  • True
  • False

Answer: True

Explanation: Qualitative risk analysis is an integral part of the planning process. It helps to understand the potential risks and their impacts, allowing for appropriate risk mitigation strategies to be included in the planning process.

Which risk assessment technique is considered a qualitative method?

  • A. Simulation
  • B. Decision tree analysis
  • C. Risk probability and impact assessment
  • D. Sensitivity analysis

Answer: C. Risk probability and impact assessment

Explanation: Risk probability and impact assessment is a qualitative method that involves assessing the likelihood and potential impact of each identified risk.

Which of the following is an OUTPUT of the qualitative risk analysis process?

  • A. Risk register
  • B. Risk report
  • C. Risk breakdown structure
  • D. Risk management plan

Answer: B. Risk report

Explanation: The risk report, which summarizes and communicates risk analysis results, is a primary output of the qualitative risk analysis process.

Risk tolerance is defined as:

  • A. The level of risk that an organization is willing to take on
  • B. The likelihood of a risk occurring
  • C. The potential impact of a risk
  • D. The process of determining the likelihood and impact of a risk

Answer: A. The level of risk that an organization is willing to take on

Explanation: Risk tolerance refers to the degree of uncertainty an organization or individual is willing to tolerate.

In qualitative risk analysis, risk urgency assessment is used to:

  • A. Determine the potential impact of a risk
  • B. Prioritize risks based on their potential impact and likelihood of occurring
  • C. Identify risks that require immediate attention
  • D. Calculate the monetary value of each risk

Answer: C. Identify risks that require immediate attention

Explanation: The risk urgency assessment is used to evaluate the need for immediate risk responses based on time sensitivity.

True or False: The risk data quality assessment is a tool used in qualitative risk analysis to evaluate the accuracy of risk data.

  • True
  • False

Answer: True

Explanation: The risk data quality assessment is a tool used in qualitative risk analysis to check the extent to which the risk is understood and the accuracy, quality, reliability, and integrity of the data about the risk.

Which of the following is a technique used in qualitative risk analysis?

  • A. Monte Carlo simulation
  • B. Sensitivity analysis
  • C. SWOT analysis
  • D. Expected monetary value analysis

Answer: C. SWOT analysis

Explanation: SWOT analysis is a qualitative technique that identifies Strengths, Weaknesses, Opportunities, and Threats (SWOT). The other techniques mentioned are quantitative.

Interview Questions

What is the main objective of performing qualitative risk analysis in PMI-RMP?

The primary objective of performing qualitative risk analysis is to prioritize identified risks based on their potential impact on project objectives. It helps in focusing on high-priority risks to devise effective risk response strategies.

How does probability and impact assessment play a role in qualitative risk analysis?

In qualitative analysis, each risk is evaluated based on its probability of occurrence and its potential impact on project objectives. These assessments help in determining the risk score which is crucial in prioritizing risks.

What kind of scale is typically used in qualitative risk analysis for rating risk probability and impact?

Typically, a relative or descriptive scale like Low, Medium, and High or a numerical scale ranging from 1 to 10 is used for rating the probability and impact of risks in qualitative risk analysis.

How is risk urgency assessment beneficial in qualitative risk analysis?

Risk urgency assessment can help to identify whether immediate attention is needed for a particular risk. Risks with high urgency might need to be addressed before other risks even if their overall ranking is lower.

What are the inputs required for qualitative risk analysis?

The primary inputs for qualitative risk analysis include the Risk Management Plan, Scope Baseline, Risk Register, Enterprise Environmental Factors, and Organizational Process Assets.

How is a Risk Probability and Impact Matrix used in qualitative risk analysis?

A Risk Probability and Impact Matrix is a grid for mapping the probability of each risk against its potential impact on project objectives. It helps in visual representation and easy understanding of the priority of each risk.

How do you categorize risks in qualitative risk analysis?

Risks in qualitative risk analysis can be categorized based on their source, their effect on project objectives, or using the project management knowledge areas. This helps in developing effective strategies to manage the risks.

What is the main output of qualitative risk analysis?

The main output of qualitative risk analysis is the updated risk register. It captures details like the prioritized list of risks, ranked list of project risks, and risks requiring immediate response.

Is it necessary to perform qualitative risk analysis throughout the project lifecycle?

Yes, it is necessary to continuously perform qualitative risk analysis throughout the project lifecycle. This ensures that the project team can proactively response to the risks as they change or emerge.

How does qualitative risk analysis help in improving stakeholder communication and engagement?

Qualitative risk analysis provides a clear prioritization of risks, reducing uncertainty and promoting understanding. This information can be communicated to stakeholders regularly, helping them understand the risk landscape and engage proactively.

How does the Organizational Process Assets influence the qualitative risk analysis process?

Organizational Process Assets can include risk categories, templates for risk ranking, previous risk databases, etc. These can significantly influence the structure, output, and effectiveness of the qualitative risk analysis process.

What role does risk appetite of stakeholders play in qualitative risk analysis?

Risk appetite of the stakeholders can influence the prioritization of risks. If stakeholders have low risk appetite, risks with lower probability but high impact might be ranked higher in qualitative risk analysis.

What is sensitivity analysis in the context of qualitative risk analysis?

Sensitivity analysis is used to determine which risks have the most potential impact on the project. It helps to understand how the uncertainty in the outcome of a project will change with different input values.

How are Risk data quality assessments carried out in qualitative risk analysis?

Risk data quality assessment is carried out to evaluate the reliability and usefulness of data about specific risks. These can include factors such as extent of understanding, data availability, quality, reliability, and integrity.

Can risks that are identified late in a project be a part of the qualitative risk analysis process?

Yes, new risks can be identified and included in the qualitative risk analysis at any time during the project lifecycle. This ensures that all known risks are examined for their impact on the project objectives.