Iterative risk assessment is a continuous process undertaken throughout the project.

  • a) True
  • b) False

Answer: a) True

Explanation: Iterative risk assessment is a process that is undertaken throughout the project’s lifecycle not just at the beginning or end of the project.

When assessing risks iteratively, the risk register is not used.

  • a) True
  • b) False

Answer: b) False

Explanation: The risk register is a critical tool used in iteratively assessing and prioritizing risks. It is continuously updated as new risks are identified, and previous ones are mitigated or realized.

The process of iterative risk assessment involves both qualitative and quantitative risk assessment.

  • a) True
  • b) False

Answer: a) True

Explanation: Iterative risk assessment involves both qualitative assessment (severity of impact, likelihood of occurrence) and quantitative assessment (numerical or monetary value of impact).

Prioritizing risks involves analyzing the potential impact of each identified risk on the project objectives.

  • a) True
  • b) False

Answer: a) True

Explanation: Prioritizing risks is indeed about evaluating the potential impact each risk can have on project objectives. Risks with higher impact or likelihood are given higher priority.

The risk impact probability chart is not used in iterative risk assessments.

  • a) True
  • b) False

Answer: b) False

Explanation: The risk impact probability chart, which is also part of the risk matrix, is often used to visually represent and prioritize risks.

Risk assessment is not necessary once project risk has been mitigated.

  • a) True
  • b) False

Answer: b) False

Explanation: Even after mitigation, risk assessments should continue as new risks may emerge, and mitigated risks may reappear.

An iterative risk assessment does not involve reassessing risks that have been previously identified.

  • a) True
  • b) False

Answer: b) False

Explanation: An iterative risk assessment does involve reassessing previously identified risks to check if their likelihood and impact have changed.

The risk urgency assessment is a part of the risk identification process.

  • a) True
  • b) False

Answer: a) True

Explanation: Risk urgency assessment, which considers time as a factor for prioritization, is an essential part of the iterative risk assessment process in project management.

Risks are prioritised based on their potential impact on cost and schedule.

  • a) True
  • b) False

Answer: a) True

Explanation: The potential impact on the project’s cost and schedule is vital in determining the order in which risks are addressed.

Communication plays no significant role in the iterative assessment and prioritization of risks.

  • a) True
  • b) False

Answer: b) False

Explanation: Effective communication is vital in this process as it allows all project members to continuously identify, assess and prioritize risks.

Interview Questions

What does it mean to ‘iteratively assess and prioritize risks’ in project management?

It refers to the continuous process of identifying, analyzing, and prioritizing risks throughout the life of a project. The goal is to continuously refine and improve risk response strategies as the project progress and as more information becomes available about existing as well as emerging risks.

Why is it important to iteratively assess and prioritize risks in a project?

This process intends to minimize the probability and impact of negative events on a project. By iteratively assessing and prioritizing risks, project managers can modify their plans and strategies in response to changes in risk status, thereby increasing the likelihood of project success.

What is the main benefit of prioritizing risks iteratively within a project?

Prioritizing risks iteratively helps ensure that attention is focused on high-impact risks which could represent significant impact to the project. It ensures that risk responses are timely and effective, helping the project to stay on track.

What are the key processes involved in iterative risk assessment and prioritization?

The key processes include ongoing risk identification, qualitative and quantitative risk analysis, risk response planning, and monitoring of risk.

How does risk identification contribute to iterative risk assessment and prioritization?

Risk identification is the first step in the process. By continually identifying new risks and changes in existing risks, the project team can ensure that every potential risk that could affect the project is taken into consideration for analysis and response planning.

Describe qualitative risk analysis in the context of iterative risk assessment and prioritization.

Qualitative risk analysis involves evaluating and prioritizing risks based on their potential impact and probability. This assessment helps in identifying which risks need immediate attention.

What does quantitative risk analysis involve in iterative risk assessment and prioritization?

Quantitative risk analysis involves numerically analyzing the probability and impact of identified risks. It provides objective and data-driven input to risk prioritization and response planning.

How is risk response planning related to iterative risk assessment and prioritization?

Risk response planning involves developing options and strategies to enhance opportunities and reduce threats to the project’s objectives. By frequently reassessing and re-prioritizing risks, maintains the effectiveness of risk response planning.

How does monitoring risks fit into iterative risk assessment and prioritization?

Monitoring risks helps in identifying any new risks, tracking identified risks, and reviewing the effectiveness of risk responses. It checks whether the risk profiles are changing, requiring re-prioritization of the project’s risks.

What tools and techniques are commonly used in iterative risk assessment and prioritization?

The most common tools and techniques used include SWOT analysis, Delphi technique, decision matrix, risk probability and impact assessment, and Monte Carlo simulation.

What is the role of a risk register in the iterative risk assessment process?

The risk register provides a record of all identified risks, including their status, owners, and plans for risk response. It serves as a tool to track how risks evolve throughout the project and how effectively they are being managed.

How does iterative risk assessment and prioritization contribute to proactive project risk management?

By continuously identifying, analysing, and prioritizing risks, project managers can anticipate potential problems before they occur, and have prepared strategies for addressing them, which is the goal of proactive risk management.

How does risk appetite affect the iterative risk assessment process?

One’s risk appetite, or the level of risk that an individual or organization is willing to accept, can affect which risks are deemed prioritizes, as well as what types of risk response strategies are chosen.

What is a Risk Breakdown Structure (RBS), and how is it used in iterative risk assessment?

A Risk Breakdown Structure is a hierarchically organized depiction of the identified project risks arranged by category. It is used to help in identifying, assessing and managing risks in a structured and comprehensive way.

Can the iterative assessment and prioritization of risks be fully automated?

While certain tools and software can assist in the identification, analysis, and prioritization of risks, the decision-making process usually cannot be fully automated, as it often requires human judgment and experience.